South Rock Construction Company schedule for paving on Centre Street - High River.

Wednesday September 27: Finish milling on 12th Avenue, 3rd Avenue SE, Highwood bridge ends, CPR rail crossing, 3rd Street NW into Eagleview, they will have flag people and one way traffic.

Thursday September 28: Guard rails removed at Lineham canal crossing and corner (flag people and one way traffic)

Friday September 29: Nothing happening

Saturday September 30: Start of paving at Highwood bridge South to 12th Avenue - Southbound lanes as they cross intersections will be temporarily closed (for approximately 2 hours) as they'repaving, ie: Macloed Trail, 3rd Avenue, 7th Avenue for a couple of hours each.

Sunday October 1: Paving - Highwood Bridge to 12th Avenue - Northbound lanes - Same closures at intersections.

Monday October 2: Paving Highwood bridge North - Highway 543 (Tounge Creek Road) to bridge - There will be flag people and one way traffic.

Note: This is a tentative schedule - depending on weather, machine break-down ect..