The Centre Street Bridge in High River re-opens today on Friday July 27 for commuters.

On Tuesday July 24 the bridge was completely closed off for ongoing construction to the floodgate.

After being closed for the past few days, the Centre Street Bridge in High River is open again.

An extra day was added to the closure this week to make sure the underground utilities were secure.

Traffic is still relegated to one way, alternating lanes until further notice.

The Town plans to have the bridge construction complete by late October.

The schedule for future closures are as follows:

Full Road Closures:

  • Wednesday, September 26
  • Wednesday, October 3

Lane Closures (alternating traffic):

  • West lane July 24 – Aug 7
  • East lane Aug. 7 – Aug. 16
  • West lane Aug. 16 – Aug. 23
  • East lane Aug. 23 – Aug. 24

 